Drawing submission deadlines and how construction management fees are calculated
Exhibition Knowledge · Canton Fair Custom Build Practice
The Canton Fair sets hard drawing deadlines by phase; late submissions lock the system and booths may be forcibly reverted to standard shells; only after drawings pass and fees are paid can you download the construction permit to move in. Construction management fees: 25 yuan/phase/m² single-deck, 45 yuan/phase/m² double-deck.
Drawing submission is highly underestimated part of custom-build participation — a day late on drawings means a day late on permits, compressing move-in and forcing extra labor and cost.
I. Deadlines set by phase
The Canton Fair sets a hard drawing deadline for each phase; late submissions lock the system. Worse, the booth may be forcibly reverted to a standard shell, wasting the entire custom-build investment.
II. The process is sequential
Submit drawings → review → revise → pay fees → download construction permit → move in and build. Any bottleneck delays everything downstream, so submit structural, fire and electrical documents completely the first time.
III. Construction management fee reference
Single-deck booths 25 yuan/phase/m², double-deck 45 yuan/phase/m², charged by booth area. The construction permit is generated only after fees are paid — don't wait until the day before move-in.
IV. Allow enough rework time
Common rejection reasons: unclear structural details, missing fire-rating labels, power load not matching exhibits. Allow at least 3-5 working days before the deadline for rework.
Field note: treat submission as a project milestone planned backwards — start design as soon as the booth is confirmed, submit drawings when finalized, and prepare electrician certificates and worker lists in parallel. Far calmer than scrambling for documents at the last minute.